Hartopp Point and Lannoy Point

Re-development of Hartopp Point and Lannoy Point
Latest updates – construction phase
So far, Higgins have been preparing the site ahead of the main construction works starting. We have now completed temporary support works to the pedestrian walkway and electrical substation connection works.
Upcoming works include:
- Installing dust, noise and vibration monitors around site
- Reducing site levels by machine dig
- Demolishing the existing brick planters adjacent to Dawes and Pellant Road
- Moving the crushed concrete on site to form a base for the piling rig which will be used to drill in the foundations for the new blocks
- Carrying out utility works next to Dawes Road. Thames Water will need to dig the pavement in some areas to connect the site to the mains water pipe
- Setting up cabins facing Dawes Road and installing a new access road. The main entrance to the site will eventually be located on Dawes Road
- We are planning to carry out foundation works between September and October 2023. This will involve holes being drilled into the ground to form the foundation piles for the new homes. After the works are completed the drainage ducts and ground slabs will be installed
We will keep residents updated if these dates change.
CCTV will be installed inside the site for security, and to control any attempted flytipping. The cameras will be positioned to ensure the privacy of residents neighbouring the site.
Meet the team event
It was great to welcome so many residents to the recent meet the team event.
The event gave residents the opportunity to meet the team and ask any questions they had about the project as well as discuss job opportunities and sample the smoothies produced on our smoothie bike. Children (and adults!) enjoyed the face painting and had the opportunity to win some raffle prizes.
The information presented at the event can be viewed here New Homes For Hartopp and Lannoy - Meet the team event (pdf 1.6MB)
Site contacts
Joan Borzak, Senior Resident Liaison Officer, Higgins
hartoppandlannoy@higginspartnerships.co.uk
07793 902544
Cristian Baltei, MCIOB Project Manager, Higgins
hartoppandlannoy@higginspartnerships.co.uk
07719 927333
If you have any questions for the council’s project team please email HLP@lbhf.gov.uk
Letters to residents
- Newsletter #2 September 2023 (pdf 324KB)
- Newsletter #1 June 2023 (pdf 355KB)
- Letter to residents works update 26.04.2023 (pdf 84KB)
- Letter to residents upcoming works 11.04.2023 (pdf 80KB)
- Letter to residents pre-construction 31.03.2023 (pdf 71KB)
Background information
Please visit Hartopp and Lannoy Points background information
- Facebook
- Flickr
- Twitter
- Youtube
- Instagram
Close menu