Estate inspection Wheatsheaf Lane Q3 - 2025 to 2026

Inspection date
1 October 2025
Next inspection date
7 January 2026

Attendees

Daniel Bitmead

Electrical Supervisor

Leanne Gittens

Contract monitoring team

Sarah Wallis

Housing Management

Housing management (for example ASB, tenancy condition and concerns)

No actions requested

Repairs

Repair requests
Action requested Location of issue Reference Target date
Refix panel lid ground floor stairs Block 13 to 18 1636578/1 Not given
Refix step nosing ground floor stairs Block 13 to 18 1636580/1 Not given

Planned or cyclical works

No actions requested

Grounds maintenance

Grounds maintenance actions
Action requested Location of issue Reference Target date
Weeds need to be cut back Around the block Not given Not given

Pinnacle caretaking

No actions requested

Other areas (for example street lighting, highways or planning)

No actions requested