William Morris House Q2 - 2025 to 2026
Inspection date
17 July 2025
Next inspection date: Check the inspection schedule
Attendees
Housing management (for example ASB, tenancy condition and concerns)
No actions requested
Repairs
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Main door to block slamming shut | Block 1 to 25 | Not given | Not given |
Repair concrete stairs on 1st, 2nd and 3rd floors | Block 1 to 25 | Not given | Not given |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
No actions requested
Other areas (for example street lighting, highways or planning)
No actions requested