Estate inspection Sulivan Court (Blocks A to L) Q1 - 2025 to 2026

Inspection date
14 May 2025

Next inspection date: Check the inspection schedule

Attendees

Daniel Bitmead

Electrical Supervisor

Stephen Mbaluka

Pinnacle (Caretaking)

Leanne Gittens

Contract monitoring team

Housing management (for example ASB, tenancy condition and concerns)

No actions requested

Repairs

Repair requests
Action requested Location of issue Reference Target date
Ease and adjust main entry door to block, not closing Block 45 to 64 324101x2 Not given
Chute on 2nd floor is broken Block 316 to 333 463001x1 Not given

Planned or cyclical works

No actions requested

Grounds maintenance

No actions requested

Pinnacle caretaking

No actions requested

Other areas (for example street lighting, highways or planning)

No actions requested

Translate this website