Cornwallis, Mackay, Canning and Charnock houses Q1 - 2025 to 2026
Inspection date
8 May 2025
Attendees
Julie O’Neil
Housing management (for example ASB, tenancy condition and concerns)
| Action requested | Location of issue | Reference | Target date |
|---|---|---|---|
| Items in communal area | Cornwallis House, block A near flat 34 | Not given | Not given |
| Items in communal area | Canning House, block A 2nd floor | Not given | Not given |
| Chute issues | Canning House, blocks A and B on floors 1, 2 and 3 | Not given | Not given |
Repairs
| Action requested | Location of issue | Reference | Target date |
|---|---|---|---|
| Override door panel loose | Mackay House, block A | Not given | Not given |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
No actions requested
Other areas (for example street lighting, highways or planning)
No actions requested